New floor register boxes set before finish flooring

Residential · Kensington, CA

Kensington Ct, Kensington: two ducted heat pumps in the crawlspace (in progress)

Underway: two Mitsubishi ducted heat pumps on framed crawlspace platforms, one per floor, with custom sheet-metal plenums and new flex distribution, built with the general contractor.

This Kensington project, now underway with a repeat general contractor partner, replaces the existing equipment with two Mitsubishi ducted heat pumps: a 2-ton system and a 1.5-ton system, one for each floor. Both air handlers sit on framed platforms in the crawlspace and feed new R-8 flex runs from custom sheet-metal plenums. Asbestos abatement is part of the scope, and a shear wall forced us to reroute the line sets and ducting and relocate the outdoor units.

Type
Full-System Residential Retrofit
Client
General contractor-led project
System
Two Mitsubishi ducted heat pumps (2-ton and 1.5-ton), one per floor
Location
Kensington, CA

Scope

  • — Removal of the existing equipment, with asbestos abatement in scope
  • — Mitsubishi SVZ-AP24NL air handler with SUZ-AA24NL outdoor unit (2 tons)
  • — Mitsubishi SVZ-AP18NL air handler with SUZ-AA18NL outdoor unit (1.5 tons)
  • — Both air handlers on framed platforms in the crawlspace
  • — Custom sheet-metal supply plenums and return filter boxes
  • — 12 to 14 R-8 flex runs per system, supply registers, two return grilles and balancing dampers
  • — About 50 ft of insulated line set per zone, condensate pumps, line-hide cover, disconnects and whips
  • — Two Mitsubishi Touch thermostats with RedLINK wireless, one per floor
  • — Change order: line set, ducting and rigid pipe rerouted around a shear wall; outdoor units relocated
  • — Startup, commissioning and final balancing

Constraints

  • — Asbestos abatement before the new work
  • — Both air handlers in a crawlspace
  • — A shear wall in the planned path forced a reroute and new outdoor unit locations

3rdGen's Role

3rdGen designed both systems and the duct layout, fabricates the plenums, installs and commissions the equipment, and coordinates the abatement and shear-wall reroute with the general contractor.

Outcome

In progress. When finished, each floor will have its own variable-speed heat pump and thermostat on new, balanced duct distribution.

Photography

Related Capabilities

Mitsubishi SVZ-AP / SUZ-AA ducted heat pumps Ducted heat pumps Crawlspace installs Asbestos abatement coordination Custom sheet metal Kensington Full-System Residential Retrofit In progress

Project Inquiry

Tell Us What You’re Planning

Home or building — pick your project type, ZIP, and timeline, then leave your contact info. We’ll review it and follow up.

We design and install complete systems in the East Bay, San Francisco and Marin. We do not do repair, service calls or maintenance.

Project category
Project type
Timeline